Kitchen Remodel Timeline: What to Expect Week-by-Week
By Admin Manager
A kitchen remodel is a major undertaking that disrupts your daily routine. Knowing what to expect week-by-week helps you plan your life during the renovation and reduces stress. Here's a realistic timeline for a typical mid-range kitchen remodel in Tucson.
Pre-Construction Phase (2-4 weeks)
Before work begins, there's important prep work:
- Design and planning: Finalize layout, materials, and finishes
- Ordering materials: Cabinets (4-8 weeks lead time), appliances, countertops
- Permits: City permits for structural, plumbing, or electrical changes
- Contractor scheduling: Coordinating trades and timelines
Week 1: Demolition & Rough-In
What happens:
- Remove old cabinets, appliances, and fixtures
- Demo walls (if layout changes)
- Remove old flooring
- Update plumbing and electrical rough-in
- Inspect for hidden issues (mold, water damage, outdated wiring)
What to expect: Messy, noisy, dusty. Your kitchen will be unusable. Set up a temporary kitchen elsewhere.
Week 2: Structural & Mechanical
What happens:
- Complete any structural changes (moving walls, beams)
- Finish plumbing rough-in
- Complete electrical rough-in
- HVAC updates (if needed)
- Drywall installation and finishing
What to expect: Still messy, but progress is visible. Inspections may occur.
Week 3: Cabinets & Flooring
What happens:
- Install base cabinets
- Install upper cabinets
- Level and secure all cabinets
- Install flooring (if cabinets sit on floor)
- Or install flooring after cabinets (if floating floor)
What to expect: Kitchen starts taking shape! Cabinets transform the space.
Week 4: Countertops & Backsplash
What happens:
- Template countertops (precise measurements)
- Fabricate countertops (1-2 weeks off-site)
- Install countertops
- Install backsplash tile
- Grout and seal
What to expect: Countertop templating happens, then you wait for fabrication. Backsplash installation is quick once started.
Week 5: Appliances & Plumbing
What happens:
- Install appliances (refrigerator, range, dishwasher)
- Install sink and faucet
- Connect all plumbing
- Test all connections
What to expect: Kitchen becomes functional! You can start using it (carefully).
Week 6: Finishing Touches
What happens:
- Install lighting fixtures
- Install cabinet hardware
- Final paint touch-ups
- Clean and polish
- Final walkthrough and punch list
What to expect: Final details complete your kitchen. Project wraps up!
Factors That Affect Timeline
Scope of Work
- Cosmetic refresh: 2-3 weeks
- Partial remodel: 4-6 weeks
- Full gut remodel: 6-12 weeks
- Layout changes: Adds 2-4 weeks
Material Lead Times
- Stock cabinets: 1-2 weeks
- Semi-custom cabinets: 4-8 weeks
- Custom cabinets: 8-12 weeks
- Countertops: 1-3 weeks after templating
- Appliances: 2-8 weeks (varies by model)
Unexpected Issues
Hidden problems can add time:
- Outdated wiring requiring full rewiring
- Plumbing issues discovered during demo
- Structural problems
- Mold or water damage
How to Minimize Delays
- Order materials early: Don't wait until demo starts
- Make decisions quickly: Delays in choosing materials delay everything
- Be available: Respond quickly to questions or change requests
- Plan for inspections: City inspections can add days
- Expect the unexpected: Build in 10-15% time buffer
Living During a Kitchen Remodel
Set Up a Temporary Kitchen
- Microwave in another room
- Mini-fridge or use garage refrigerator
- Paper plates and disposable utensils
- Electric skillet or hot plate
- Cooler for beverages
Plan Meals
- Eat out more (budget for this)
- Meal prep before demo starts
- Use slow cooker or grill
- Stock up on non-perishables
The Bottom Line
A typical mid-range kitchen remodel takes 6-8 weeks from start to finish. Full gut remodels with layout changes can take 10-12 weeks. The key is planning ahead, ordering materials early, and being flexible when unexpected issues arise. Good communication with your contractor helps keep things on track.